Descending: Apply a percentage of the requirement on the remaining days.
Constant: Requirement is always the total quantity.
Ignore past: Requirement is applied to the first day of period.
Example: Today is 25th November of 2016 and there are 2 forecasts, one by week and second one by month. Quantity for both forecast are 100 Pieces.
An MRP executed today provides the following results.
Calculation By Week:
Descending: Quantity = 42,85. We apply a % of pending days. Complete week days are 7, pending days are 3 (Today is Friday 25) then 3(days) * 100(Pieces) / 7(days)
Constant: Quantity = 100. We can execute the MRP each day of the week, the result is the full quantity.
Ignore past: Quantity = 0. Quantity is considered only on the first day of period (In our example day 21 of November, first day of the week).
Calculation By Month:
Descending: Quantity = 20. We apply a % of pending days. Complete month days are 30, pending days are 6 (Today is friday 25) then 6(days) * 100(Pieces) / 30(days)
Constant: Quantity = 100. We can execute the MRP each day of the week, result is the full quantity.
Ignore past: Quantity = 0. Quantity is considered only on the first day of period (In our example day 1 of November, first day of the month).
|