Exploit Full Capacity

Top 

This method checks the total available capacity on a day for a resource.

Note: It does NOT check when the capacity is available.

 

APS_Exploit_Full_Capacity_01

Example 1:

2 work orders, one routing position per work order, each routing position with a total duration of 6 hours. Both work orders are planned in APS with forward scheduling and with the same start date/time.

The result of an APS forward scheduling will be:

Both work orders will have the same start date and time because Work order 1 needs 6 hours and 6 additional hours are available for Work order 2. The start/end time of each work order is not checked by Beas.

APS_Exploit_Full_Capacity_02

Example 2:

2 work orders, one routing position per work order, each routing position take 8 hours. We have a total duration of 16 hours for both work orders with a total available capacity of 12 hours on the machines.

The result of an APS forward scheduling will be:

APS_Exploit_Full_Capacity_03

Here again both work orders start at same time but the time span by which Beas assigns the second work order is longer. The routing operation of the second work order will still be 8 hours (as well as the capacity occupied on the resource), but can take only 4 hours from Day 1 and will have to take 4 hours from the second day. This is why you will have representation in the APS GANTT for the second work order that is longer than the first one. If you check the Resource > Dispatches > Detail, you will see the calculated time zones for the second work order: Day 1:  6am – 10am ( 4 hours, as the remainder of the capacity has been taken by work order 1) Day 2:  6am – 10am (the remaining 4 hours of work order 2)

 

Example 3:

Work order 1 and 2 have been set to start on the same Day by APS with forward scheduling. Each of the work orders has one routing position and each of them lasts for 6 hours. You have assigned a resource allocation of 50% for each of the routing positions.

APS_Exploit_Full_Capacity_04

 

In this situation, the Detailed planning will not be used.

The result of an APS forward scheduling will be:

The system plans the complete day, but on both work orders it will have the same start date/time, and they will be in parallel because of the 50% setting at the routing position resource allocation. The system will represent both work orders with a longer time span (12 hours each), but each of them will still occupy only 6 hours of resource capacity.

APS_Exploit_Full_Capacity_05

See Capacity planning - APS, Detailed planning