Overall Utilization of Resources (Groups)

Beas dashboards > Using the dashboards > Capacity Utilization > Actual and Planned Utilization Tab > Overall Utilization of Resources (Groups)

Top  Previous  Next

Dash_4.1.3_a

 

This report details how the capacities of the entire resource groups are used, revealing the following information:

a)Setting-Up: Total setup times registered for the resources;

b)Working: Total scheduled and executed work times registered for the resources;

c)Interrupted: Total interruption hours registered for the resources;

d)Free: Remaining capacity after discounting interruptions, scheduled work, setup times, and work times.
 

By default, three colors can be applied to the report rows. The colors can be customized by editing the dashboard and defining new color rules.

Red: Free capacity greater than 80%, or less than 20%;

Yellow: Free capacity between 40% and 80%;

Green: Free capacity between 20% and 40%;
 

Any resource group can be selected for further insights on how the capacities are or were used (triggering filters on the other reports and charts from the dashboard). If you wish to check how the capacities of a single resource group were used, you can just click on the desired resource group and check the results under the Capacity Utilization Overview (Hours), the Resources’ Utilization Chart, the Daily Utilization View, the Monthly Utilization View, and Overall Utilization of Resources sections.

 