Scrap of Material %
|
Material scrap%.
|
Number of payslips
|
Information field - may be used for printing payslips.
|
Barcode
|
This number can be printed as bar code on the work order. Using this bar code you can logon to this operation in terminal
The number is generated automatically. It is a continuous number, which cannot be manipulated.
See
Report order times
Logon order
Logoff order
(Field: BEAS_FTAPL.NUMMER)
|
|
Task
|
Link to a Project-Task .
|
Block login
|
Check mark, to block logon to this operation.
|
Confirmation (Time receipt) in Unit
|
Selection of time receipt units. See: Units of measure.
|
Factor per Production UoM
|
Conversion factor to warehouse unit. See: Conversion.
|
Block completion with quantities below minimum
|
Block completion with less quantity .
|
Invisible in post-calculation
|
If active, the position is hidden in post-calculation .
|
Expand to cost elements
|
Drop down: if you expand to several cost elements, you can separate the costs at a time receipt and distribute them to the cost elements set up previously.
Note: To avoid incorrect operation time: After reducing the number of cost elements, delete the prices of the cost elements not in use.
|
Resource optimization
|
Check mark, if resource optimization was enabled.
|
Slave op.sequ. belongs to Master
|
A master operation sequence can be selected. Information on the master-slave concept .
see Slave-to-Master.
|
Image
|
Image for this operation, for better recognition.
|
Color
|
Operation is displayed in this color in all windows.
|