Scheduling: Forward

Production > Capacity Planning, APS > Work with APS > Scheduling: Forward

Top  Previous  Next

Use forward Scheduling for

 

plan exact start date for every routing step

if you need resource resource-optimized planning

 

The forward scheduling starts with defined Start date and calculates the complete structure.

The system starts with the sub level and then with the main level.

 

In this example

"Assembly 1" can be produced only after all sub-assemblies have been finished.

last operations of the sub-assemblies are linked to the first operation of "Assembly 1".

 

forwardscheduling

 

In APS Gantt view

forwardscheduling2

 

Note:

For forward scheduling you need a APS License