Edit resource group

Production > Resources > Resource Groups > Resources group administration > Edit resource group

Top  Previous  Next

PATH: Resources > Resource Master Data> Select a Resource > Edit Group button.

Resource_group_A

Window stamm_arbplatzgruppe_edit.psr

 

Resource group Tab

Header

Field

Description

Group

Group ID.

Description

Description of the group.

Directly schedulable

If enabled, each resource of this group can be scheduled separately. You can assign an ID to the scheduling.

Automatic optimization

If enabled, automatic optimization is used for the pre-selected resources of the resource group.

Double-click the Optimization_icon / Expand_2023_04 icon to open the Optimization: Sequence window and select the resources to be optimized:

Optimization_browse
Window stamm_arbplatz_optimize.psr

With ID

Only visible if "Directly schedulable" field is enabled.
ID of the resource that is linked to the current Resource Group.

 

Functions:

Field

Description

Remove

Delete selected resource group from the list.

Refresh window

Update window after changes.

Set up Optimization

Opens the Optimization: Sequence window.

New Resource

Opens the Resource Create window.

Resource Delete

Opens the Resource Master Data window for the selected resource to delete. Deletion is prompted.

Resource Edit

Opens the Resource Master Data window for the selected resource.

 

 

Resources sub-tab:

All resources of the group are displayed with corresponding cost rates.

Field

Description

Resource

Number of the resource.

Description

Description of the resource.

Service/cost

Enable to consider the respective resource in scheduling.

Full cost rate

Full cost rate deposited in master data of the resource.

Marginal cost rate

Marginal cost rate deposited in master data of the resource.

Planned capacity

According to factory calendar (hours per day).

Empl./No.

Number of machines/ employees.

Group

Group ID.

 

Scheduling sub-Tab:  

The factory calendar with registered capacities of the resource group is opened.

Resource_Group_Scheduling
Window stamm_arbplatzgruppe_edit.psr

 

Utilization is displayed for each resource of the group.

 

Graphic sub-Tab


Help URL: https://help.beascloud.com/beas202402/index.html?ressourcengruppe_bearbeiten.htm