ViewsProduction > Capacity Planning, APS > APS Planning > APS Edit Planning > Views > Views |
Top
Previous
Next
|
|
In this Tab you can define how the WO will be displayed in the Gantt. Production > Capacity Planning > APS > Add > Views tab
Window fert_xgantt_view_browse.psr Default button: Sets the selected row as default.
Production > Capacity Planning > APS > Add > Views tab > Add or Open |
Field |
Description |
|||||||||||||
View |
Unique name of the view |
|||||||||||||
Description |
Description of the view. |
|||||||||||||
Show only selected resources |
Only resources will be shown which were selected in the planning (APS / VIEW). The operation sequences will not be linked to the arrows. Resources can be arranged in groups in the Gantt view. |
|||||||||||||
Date area from today minus days |
Define the time range in which the work orders are going to be displayed. This is defined in calendar days. Example: If the user enters from “1” to “30”, all work orders are displayed from 1 day in the past to 30 days in the future. |
|||||||||||||
Optimal daily adjustment |
Determine whether the day view should be scaled automatically. In most cases, it is better not to use this parameter and to define a fixed value. |
|||||||||||||
Scrolling mode |
|
|||||||||||||
Xgantt Style |
- Fiori style (old): View APS results as in Beas Manufacturing versions older than 2021.03 - Boyum new Style: View APS results that is based on Boyum color codes and fonts, and that provides enhanced user experience. See Boyum new Style Gantt viewer. |