Scrap of Material

Concepts > Scrap > Scrap of Material

Top  Previous  Next
Expand/Collapse Toggles

In Routing position > Extended you can define the Scrap of Material related to a routing position.

 

Example:

You must produce and fill 6 kg of paste

15% is lost during filling

Now it must be calculated how many liters of paste are needed.

 

Calculation

Correct formula is: Quantity: (100  – scrap% )  * 100

 

If you need 6 kg of finish product, then you need

6 kg : (100 -  (0.15) * 100 = 7.059 kg paste

 

If you see the opposite:

I fill 7.059 kg paste and lose 15% =

7.059 - (7.059 / 100 * 15) = 6 kg

 

In the Configuration wizard > "Behavior for Routing Scrap of Material % affect to" you can define how the program should work.

 

 

The following settings are available:

hmtoggle_plus1Only the linked material is affected by the Scrap % setting

Result see this example:

Precalc_Rout_Scrap

hmtoggle_plus1All materials under the last linked materials are affected

This is the Standard setting

Precalc_Rout_Scrap_02

 

Example: When a bar is sawn, a scrap rate of 10% may be incurred. If the material is ground, the bar becomes even shorter, that is a longer length must be cut beforehand,

 

routingscrap_03

 

Example:

We need a finished product with a length of 250 mm.

 

We start with 308.65 mm - sawn : scrap 10% = 277.78.

Continue with  277.78 mm - ground : scrap 10% = 250 mm.

 

Routing Position

Material

Quantity

Scrap %

10 sawn

bar

308.65 mm

10

20 ground


277.78

10

30 QC


250 mm


 

Calculation

 

Correct formula is: Quantity : (100  – scrap% )  * 100

 

Position 20 we need 250 : (100 – 10) * 100  = 277.78

The value is entered into the production BOM item, column "calculated scrap" as fix value.

 

hmtoggle_plus1All materials are affected by the Scrap % setting

Precalc_Rout_Scrap_03

 

Notes:

This field is only visible, if in Configuration wizard > Master data > routing > operation related material scrap" is enabled.
The Item Report – Item Structure report does not support the Material Scrap factor on Routing Level.
Enable this option only if absolutely necessary; the computation will take considerably longer.
In work order this field is blocked, because scrap of material is determined only at the moment of creating the work order
When checking which routing positions are considered, the following criteria apply:
- Validity date
- Active (no formula, no quantity check)
- Variants (A–Z)
Not checked:
- Variants formulas, Product configurations

Help URL: https://help.beascloud.com/beas202102/index.html?conceptscrapofmaterial.htm