Plan = actual if no conformationAdministration > System Initialization > Configuration Wizard > Calculation > Post calculation > Plan = actual if no conformation |
Top
Previous
Next
|
This setting allows to define Planned costs as Real costs if there is no Time receipt.
PATH: Administration > System initialization > Configuration wizard > Calculation > Post Calculation > Plan = actual if no confirmation
In the following example, there are 4 Routing positions, 10 + 20 with "Clock mandatory" active and 30 + 40 with "Clock mandatory" = disabled For Position 20 and 40 there are time receipts booked.
Post calculation returns the following result: Duration (and costs) for Position 10 and 30 = 0
With definition "only not Clock in/Clock out Mandatory" the system uses Planned Time for all routing positions without time receipts, if Clock Mandatory is disabled in this Routing position. In the following example you can see the planned time as real time in line 30 with no time receipt.
With definition "only Clock in/Clock out Mandatory" the system uses Planned Time for all routing positions without time receipts, if Clock Mandatory is enabled in this Routing position. In the following example you can see the planned time as real time in line 10 and no time receipt.
with Option "All" the system ignores "Clock in/Clock out Mandatory" and checks all routing positions without time receipts.
This setting is used for Post calculation and assembly valuation.
Parallel routing position is calculated too in case there is no time receipt booked for the parallel position. It uses the "Clock in/Clock out mandatory" flag from main routing position. Example with setting "All":
Parallel position for main Position 10 and 20 do not have a time receipt. Beas uses Planned Duration/Costs for the parallel positions.
if there is time receipt for the parallel resource, the system takes the sum of time receipt:
(Variable bdeohnezwangbewertung J/J2/J3/N Standard=N) |