Factory Calendar

Administration > System Initialization > Factory Calendar

Top  Previous  Next
Expand/Collapse Toggles

PATH: Administration > System initialization > Factory calendar.

In this window you can define the main day planning. You can set:

- holidays

- availability in % for Machine resources and for FDC with graphical visualization

 

Beas uses this calendar for planning hours of machine resources and human resources

 

Machine Resources

Capacity of resource  = hours / day of resource * count of resources * calendar day %

 

Human Resources (FDC)

Presence to be = count of hours (shift definition) from current day template *  calendar day %

 

After changing the calendar, the resource planning and human "present to be" time must be recalculated.

This takes place as an automatic process.

 

See the following links:

Calendar Creation

Day Template

Shift schedule for Resources

Attendance Recalculation


IMPORTANT: If the B1 UP Usability Package Add-On is installed, but you cannot see Beas Production or Beas Maintenance Calendars, restore calendars as described in B1 UP Usability Package Documentation.

 

Factory calendar_9.3.02

Window bde_kalender_browse.psr

 

It is possible to define up to 6 calendars + a basic calendar.

Human shift planning uses only the basic calendar.

For resource planning it is possible to use the basic calendar or calendars 1–6.

 