aps

Follow Events available

 

Events

Description

StartCalculation

In APS List the calculation is started

StartWorkorderPosition

Calculation of work order position started

StartWorkorderPositionStep

Work order position - Step started

(<<) StartCalcRoutingPositionBackward  

Start Routing Position Backward calculation

(<<) MiddleCalcRoutingPositionBackward

Middle Event

(<<) EndCalcRoutingPositionBackward

End Routing Position Backward calculation

(>>) StartCalcRoutingPositionForward

Start Routing Position Forward calculation

(>>) MiddleCalcRoutingPositionForward

Middle Event

(>>) EndCalcRoutingPositionForward

End

CalcRoutingOverlapping

Calculate overlapping in forward calculation

EndWorkorderPositionStep

Work order position - Step end

EndWorkorderPosition

Calculation of work order position end

EndCalculation

In APS List the calculation end

 

Tables, which you need for own calculations

Table

Description

BEAS_RESOURCE_CALENDAR

Resource calendar

BEAS_RESOURCEN

Reserved times