All properties of a Precalculation can be defined in the header. The Item field is mandatory.
PATH: Sales – A/R > Precalculation > Open precalculation > Open calculation.
This window opens from various locations:
•if you create a new calculation from a sales order
•if you create a new calculation from a sales–precalculation
•if you make a double-click on the first row in the precalculation
Window pk_haupt_edit.psr
Master data header
|
|
Doc.No. ( Ref.No)
|
Calculation number and quotation or order allocation number.
The first number is a sequential, unique number which is automatically assigned.
The second number is only assigned if the calculation was created from a quotation or order. This number is also entered in the quotation or order.
|
Item
|
Item number.
|
I-Version
|
Item version number as per version number determination, if item version control was enabled.
The following information is determined based on version:
•BoM
•Routing
•Description
•Drawing number
See
Item master – I-Version
|
|
Revision
|
Revision number of the calculation (text only).
|
Variant
|
Item variant.
|
Configuration
|
Link to a configuration.
|
Tab Project
|
Project definitions
|
Tab Valuation
|
Lot size, Valuation, Tools
|
Tab Weight
|
Values regarding weight: net weight, gross weight, UoM and Factor.
|
Additional header tabs
|
|
Calculation
|
Scale prices: Required time, material and manufacturing costs, contribution margin, and so on per scale. See Material scale prices
Cost Element: Time types with marginal and full costs, and surcharges. See cost elements.
Cost element: view stored cost element groups.
|
|
Item
|
Opens a copy of item master data, which can be changed for this calculation.
|
Result
|
View the results of all calculation objects.
|
Price list: The button opens the price list window of the selected item in the calculation.
Window artikel_edit_preisliste.psr