BoM Scrap

Concepts > Scrap > BoM Scrap

Top  Previous  Next

Indicate material scrap which is added to the calculated requirement.
 

scrap_bom_jav

 

Note:

This field is visible in Master Data and Precalculation.

In Work orders you can see the calculated scrap.

 

Set the formula to be used in the Configuration Wizard.

Available formula definitions:

Scrap = Quantity * ( Scrap % )    (= default setting)

Scrap = Quantity / ( 1 - Scrap%/100 )

 

Example:

Definition with Scrap = Quantity * ( Scrap % )

Requirement: 10 Pcs
Scrap: 10%

Total requirement: 11 Pcs

 

Definition with Scrap = Quantity / ( 1 - Scrap% / 100 )

Requirement: 10 Pcs

Scrap 10%

Total requirement:

 