(>>) MiddleCalcRoutingPositionForward

Executed during the capacity calculation of every routing position after the calculation of transfer time, at the beginning of a routing position and before the calculation of transfer time.

Only Forward calculation

 

You can change the start time for work time, but you can move only forward, because transfer time is calculated.

 

aps_routingcalculation_forward

 

 

Variable

Read

Write

Description

e_Method

x


Calculation Method

MRP Executed by MRP, ATP, CTP

Workorder Executed manually from work order

Or the Calculation Method, which defined in APS List

e_MethodStep

x


In the Method you can define more than one step. This is the step. First step is 1

e_DocEntry

x


Work order document number

e_LineNumber

x


Work order position number

e_LineNumber2

x


Routing Position

e_BaseDocEntry

x


Base document, example Sales order. Only in MRP

e_BaseLineNumber

x


Base document line

e_ItemCode

x


Calculated Item Code

e_Quantity

x


Calculated Quantity

e_CheckReservedTime

x


Check reserved times

e_RoutingSplitt

x


Allow Routing Split true/false

e_Simulation

x


Simulation true/false

e_CalcSaveType

x


Save type

Type

Description


Normal

S

Simulation. Don't save time reservation

I

Simulation. Save nothing

R

Calculation for alternative resource with checking Time reservations

P

Planning: Save all results

e_ReservationType

x



e_Resource

x

x

Resource ID

If you change the resource, the system makes only the time reservation on this resource, but does not change the resource on the routing position.

e_TimeLine

x

x

Time line in format yyyy/mm/dd hh:mm

Backward: The End Date

Forward: The Start Date

 

Note: The time line is between transit and idle time.

In forward calculation you can go only forward in time line

In backward calculation you can go only backwards.

 

 

e_Duration

x

x

Duration in minutes

 

Every Date must have the following format: yyyy/mm/dd hh:mm

If you use another format, the system will not save the value correctly.

 

NOTE:

The system does not check the changes.  If you change any parameter, you must check all / calculate other parameters too.

The system saves the changes in the Work order routing position, but this does not affect time reservation table BEAS_RESOURCEN!