Projection of actual costsConcepts > Post-calculation > Projection of actual costs |
Top
Previous
Next
|
Post-calculation offers a function to calculate the expected costs of a given quantity based on the on previously reported quantities. Costs for material, operations, and quantity, depending surcharges are calculated.
Example: Operation with costs of 2€/Minute Planned quantity: 10 pcs
This function is useful for actual costs evaluation methods with partial postings.
Example: 1. Operation planned: 10 minutes, costs 2€/minute 2. Operation planned: 10 minutes, costs 2€/minute Planned 10 pieces, Partial completion 5 pieces Planned costs: 1. operation 20 €, 2. operation 20 € = 40 = 4 € per piece
This example shows the difficulties of partial postings without projection. The first 5 pieces are valued at 6€, the next 5 pieces at 2€. In certain configurations even negative evaluations are possible.
Material evaluation example: A BOM item has a requirement of 1 per 1 assembly and a value of 3€ Production quantity = 10
Webinar Product Cost determination from 2017/06, Part "Quantity Projection"
Example: Projection of actual costs
|