| Scheduling: ForwardProduction > Capacity Planning, APS > Work with APS > Scheduling: Forward | Top 
     Previous 
     Next | 
| Use forward Scheduling for 
 •plan exact start date for every routing step •if you need resource resource-optimized planning 
 The forward scheduling starts with defined Start date and calculates the complete structure. The system starts with the sub level and then with the main level. 
 In this example ▪"Assembly 1" can be produced only after all sub-assemblies have been finished. ▪last operations of the sub-assemblies are linked to the first operation of "Assembly 1". 
 
 
 In APS Gantt view 
 
 Note: For forward scheduling you need a APS License |