A QC plan can be stored in a work sequence. Choose at which moment the QC order should be created: 
  
Manually: Only manual creation 
At time receipt: Creating during the first "Time receipt" 
At login to work order: Creating during the first logon (not the first time receipt) 
Production create: At new creation of a work order (beas9.0-000-003-001) 
  
External operations 
If dealing with an external operation, the option is supported. 
At order logon: Creating a purchase order. 
At time receipt: Creating goods receipt. 
Note: for external operations, there is no link from QC order to purchase or goods receipt. Only a link to operation.  That means, there is always only one QC order per operation, with any number of samples. A dependency from external operation-goods receipt cannot be created.  
  
See  
Routing 
Production – operation sequence 
Quality control order 
(Variable fert_qsanlage, m (default) = manually, r = at time receipt, s = at order logon, c=at new creation) 
 |