Position 
 | 
Unique position number – normally in increments of 10 to add subsequent positions. This number also serves as sort criterion for the terminal display. 
 | 
Type 
 | 
Selecting the resource type with a right-click. 
 | 
Resource 
 | 
Designation of the resource – depending on the type selection, the resource can be selected with a right-click. 
 | 
Description 
 | 
Designation of the resource – is automatically carried forward after selecting the resource. 
 | 
Quantity 
 | 
Overall demand of the resource, e.g. number of tools. 
 | 
Setup time 
 | 
The setup time in 'per' according to the field "Time per". 
 | 
Mach+Labor Time/unit 
 | 
The mach+labor time in 'per' according to the fields "Time per" and "Quantity per". 
 | 
Additional Info 
 | 
Any additional information displayed at the FDC terminal of a tool. 
 | 
Utility factor 
 | 
The utility factor – the inverse of work steps. See Calculation of target time.  
Example: By sawing a board apart, the material is provided for two finished goods - the utility factor is thus 2.  
 | 
Number factor 
 | 
The opposite to the utility factor.  
Example: Two steps are necessary to produce a part. The time per 1 cut is stored, the quantity of the required cuts is stored with number. 
 | 
Quantity per .. 
 | 
The requirement time is specified for each number indicated here per assembly to be produced. 
Example: For 1000 the time is per 1000 finished parts. 
 | 
Time by 
 | 
Times are specified in hours or minutes. 
 |