In Item Master Data > Planning Data tab you can define Tolerance days.

mrp_tolerance0

 

Related to order scheduling: If there is negative stock in the time line, the item will be shown in MRP as shortage. Here you can enter the number of days. A negative balance will be tolerated.

 

Example:

Stock = 0

Sales order = 3rd May
Purchase order delivery date = 6th May

Material comes 3 days late

mrp_tolerance1

 

If tolerance date for this item is defined with 3 days or more, the result is: OK

If tolerance date is < 2, the MRP must inform you.

 

In MRP the filter "Only shortage" means:

Display all entries which have a negative balance in the timeline.

Order_Rec_Filter_NEW

(MRP Filter - Predefined Filter)

 

In this example the item has a balance from 0, but a negative balance between 3 and 6 May

MRP displays this item if the item has "tolerance days" < 3 days.

MRP does not display this item if the item has a "tolerance days" > 3 days.

 

Negative Balance in past

Negative Balance in past will be ignored entirely.

The calculation for the time area starts from the current Date.

 

Example:

Today is 5th May

Sales Order is 3rd May

Delivery = 6th May

 

The system calculates: Balance is negative from 5th – 6th May = 1 day.