Standard costs method

Concepts > Post-calculation > Standard costs method

Top  Previous  Next
Expand/Collapse Toggles

Using the standard cost method, the total value and the value of the parts of an assembly can be identified,  such as materials, manufacturing costs, tool costs, or other surcharge costs. Standard cost means, that these values are not dependent on the volume of the production, only the budget figures are taken into account.

 

The standard cost method involves an entire workflow:

Pre-calculation via batch pre-calculation

Pricing on basis of the pre-calculation

Copy of evaluation into the work order, including the calculation scheme. The work order is now firmly attached to the pre-calculation

Postings are performed with the current standard cost rate

 

Configuration Wizard > Production > Valuation and booking of the assembly > Valuation > Valuation of the assembly by "standard cost method"

The Max time for last calculation field is displayed. This is the update interval for batch calculations. If the entered time is exceeded, no work orders can be created.

eass standardkostenv

 

A correctly set pre-calculation valuation method is crucial. Set to "Item valuation". Set all items  to "standard price".

Configuration Wizard > Calculation > Precalculation > Material pricing to "Item valuation method"

precalc_std

 

Inventory> Inventory Transactions > Batch calculation

Setup a calculation for calculating standard costs

The price list or price calculation does not need to be filled. Select the desired evaluation method in Pricing and Enter calculation price, and the type of pricing procedure. One step evaluation can be enabled for standard cost.

precalc_batch

The defined calculation should be performed regularly and the update interval can be set in the Configuration Wizard. After calculating, change to the results tab and perform an inventory revaluation.

 

Note: If the price per warehouse is set, the batch calculation needs to be performed per warehouse. See Batch-calculation.

 

Connecting to a work order

All the work orders that are being created for the items, are referring to the calculated standard costs. The connection to the standard costs calculation is available in:

 

standardkosten link zu fa

 

Valuation of assembly – Standard cost method

Concept: Valuation of assemblies