Separate setup costs

Production > Resources > Edit resource > Costs tab > Resource costs > Separate setup costs

Top  Previous  Next

The processing and setup costs can be assigned different cost rates and can be reported separately. Also see Separate wage costs.

 

This is activated in the Resource Master Data > Cost tab.

Set the Expand to cost elements parameter to 2. This makes the processing and setup time available as different time types and you can store the cost rate per minute at marginal and full costs.

Resource_Cost_Pers_SAPStyle

 

In this example, the labor costs are also activated, but this is only possible if machine grouping is not used. Alternatively, the personnel costs can be factored into the setup and processing time.

 

The setup costs can now be displayed separately in the calculation. See setup of calculation objects in Separate wage costs.

ressourcesetup2

Window pk_struktur.psr

 

This example illustrates that 5 minutes of setup time and 10 minutes of processing time was used and the person, who may only operate one machine, generated both values (setup + processing time), that is, 15 minutes of cost for this work sequence.

 

This has the following effect in the area of production:

A resource is stored in a work sequence with the corresponding setting.

WO_edit

Window fert_arbplanos_edit.psr

 

If the work sequence is now logged in, the employee can choose whether to log in the setup time or machine time.

ressource1

 

WO_login_order_Terminal

Beas determines which functions are available directly from the master data and resources rather than the work sequence as the information in the work orders represents the plan data.


Help URL: https://help.beascloud.com/beas202106/index.html?separate_ruestkosten.htm