DIH Work Order

Administration > Data Integration Hub > Data integration hub > Import Definition > Definition Data Target > DIH Work Order

Top  Previous  Next
Expand/Collapse Toggles

Imports Work order definitions.

A work order has the following objects:

Work order header

Work order position

Work order bill of materials and routing position

 

hmtoggle_plus1Migration from old or third-party application
hmtoggle_plus1Creating bill of materials synchronization between third-party application and Beas

Area

Insert

Update

Work order header (BEAS_FTHAUPT)

Use this if you want to update the header information or if you want to create new work orders and  you need only the item code and quantity for the work order position.

Inserts all header information.

Inserts first work order position with item code and quantity.

Beas explodes the bill of materials, routing position and all order-related sub-assemblies.

Note:

Creating reference to other documents or changing any properties in the work order line is not possible.

You can change the work order type, but it is not possible to change the work order type related flags; Beas ignores these changes.

 

You cannot define the document number (BEAS_FTHAUPT.BELNR_ID), only the order number (BEAS_FTHAUPT.AUFTRAG).

Most properties are changeable, but you cannot change the created work order positions.

 

Beas will ignore the item code and quantity property.

 

Work order position (BEAS_FTPOS)

Use this to import work order positions with extended position information.

The assembly can be defined, but Beas always uses the BOM and routing information from item master data.

Add position to existing work orders.

Beas explodes the bill of materials, routing position and all order-related sub-assemblies.

If you do not define a work order number, Beas creates a new work order (BELNR_ID=0).

It is not possible to define additional information for work order header if the system creates a new work order.

 

Defines linked information.

It is not possible to update existing positions.

Bill of materials (BEAS_FTSTL)

Use this to synchronize the BOM with external programs.

you can add and change bill of materials position of existing work order positions.

The work order document number, work order position and bill of materials position are mandatory.

 

When trying to insert an exiting BOM position, Beas updates the position.

 

Beas does not explode order related assemblies. Multilevel work orders cannot be created.

All properties of an existing bill of materials position can be updated.

 

Beas does not change existing sub-position.

 

You can delete a BOM if you set the quantity to 0, but only if no related transaction or reservation exists.

Routing position

Not possible.

Not possible.

 

hmtoggle_plus1Import WO BoM details

Help URL: https://help.beascloud.com/beas202106/index.html?dih_work_order.htm