Resource scheduling (MRP2) is based on lead time calculation. Therefore "Calculate lead time for assembly" must be activated if resource scheduling is required.
If enabled, lead time is calculated using the integrated capacity planning tool based on the routing production times defined.
The calculation is carried out by means of backward scheduling simulation. Existing capacities are not taken into account. If a material is assigned to an operation sequence directly, then the start date of the operation sequence is assigned (time: start of processing).
Depending on the depth of the production structure and the accuracy of the forecast, the computation can by time consuming.
If disabled the item lead time and the lead time defined in the Configuration Wizard serves as a reference. The calculation time is significantly shortened. The "Resources - Activate resource planning function is disabled.
Note: Lead time means production time of the assembly without consideration of sub-assemblies lead times.
Example
Example: Here is the item structure:
Assembly A (Lead time = 10 work days)
Assembly B (Lead time = 5 work days)
The date of finished production A and B is the requirement date
Start date A: Requirement date – Lead time A (10 days)
Start date B: Start date A – Lead time B (5 days)
See: calculate resources
|