Advance Planning

Inventory > SAP Item Master Data > Advanced Production > Advanced Scheduling

Top  Previous  Next
Expand/Collapse Toggles

This section of the Advanced Production tab includes Beas fields associated with MRP scheduling.

 

Accumulation

Detail

Every requirement originator (forecast, purchase order, sales order, etc.) is displayed separately. This setting makes sense if purchasing on an order basis or in the case of high-quality goods.

Day / week / month / sum

The requirement originators are accumulated according to the period selected here:

e.g. requirement per day – only the accumulated quantity issued and received per day / week / month is displayed in the MRP run in this case, not the requirement originator.

Performed for "Sum" setting.

If detailed specification of the requirement originator or resource is not necessary and high data volumes are incurred, this type of accumulation is recommended. The calculation time is shortened, the view is easier to understand.

 

Note

This setting is available in MRP as well. Always the rule applies with the highest summation.

 

Example:

Item: Detail, MRP: Day: summed by day
Item: Tag, MRP: Detail: only this item is summed by day
Item: Tag, MRP: Month: summed by month

 

see MRP Wizard Planning scenarios Detail

Computation duration

Priority

The MRP run can be sorted by priority. If a material has a high priority and a requirement, the requirement-originating assembly also receives the corresponding priority.

You can configure whether a high or low number displays a high priority in the Setup Wizard (ascending or descending).

MPS

Activate if an item is scheduled via MPS.

 

 

back to Item Master Data