Executed Production

Beas dashboards > Using the dashboards > Production Planning Overview > Execution Overview Tab > Executed Production

Top  Previous  Next

Dash_3.3.5

 

This grid shows all the executed routing positions for the current set of filters and selections.
 

a)Status: Routing position status, which can be “Partial” or “Complete”:

 Partial Dash_orangedot: Routing position partially executed, but remains open waiting for more time receipts;

 Complete Dash_3.1.1_a: Completed and closed routing position.

b)Effective End: Last time receipt’s end date and time for the routing position;

c)Planned End: Planned end date and time for the routing position;

d)Detailed Status: Specific status to help understanding the situation of each routing position:

 Closed routing positions:

         Finished on Schedule: Routing position closed during its scheduled dates;

         Finished in Advance: Routing position closed before its scheduled dates;

         Finished Overdue: Routing position closed after its scheduled dates.

 Open routing positions:

         Planned Operation: Routing position with end date scheduled for today or for the future;

         Overdue Operation: Routing position with end date scheduled for past days.

e)WO: Work order number, position number, and routing position number;

f)Resource: Description of the resource;

g)Item Name: Description of the item;

h)Operation Desc.: Description of the routing position;

i)Operator: Name of the operator that registered time receipts for the routing position. When more than one operator have worked on the same routing position, all of them will appear as individual rows in the “Executed Production” grid;

j)Time (Pl./Act.): Times (planned / actual). A blue progress bar represent how much of the planned times were already reported and, in the cases where actual times surpassed the planned times, the values are highlighted in bold dark red Dash_45-60_b;

k)Qty. (Pl./Act.): Quantity (planned / actual). A blue progress bar represent how much of the planned quantities were already produced and, in the cases where actual production surpassed the planned amounts, the values are highlighted in bold dark gray Dash_100-150;

l)Scraps: Amount of scraps registered for the routing position and their representativeness over the produced quantities.


Help URL: https://help.beascloud.com/beas202402/index.html?executed-production.htm