Post-calculation offers a function to calculate the expected costs of a given quantity based on the on previously reported quantities. Costs for material, operations, and quantity, depending surcharges are calculated.
Example:
Operation with costs of 2€/Minute
Planned quantity: 10 pcs
|
without projection
|
with projection for 1 piece
|
with projection for 10 pieces
|
1 minute, 0 pieces reported
|
2 €
|
0 €
|
0 €
|
1 minute, 1 piece reported
|
2 €
|
2 €
|
20 €
|
5 minutes, 2 pieces reported
|
10 €
|
5 €
|
50 €
|
This function is useful for actual costs evaluation methods with partial postings.
Example:
1. Operation planned: 10 minutes, costs 2€/minute
2. Operation planned: 10 minutes, costs 2€/minute
Planned 10 pieces, Partial completion 5 pieces
Planned costs: 1. operation 20 €, 2. operation 20 € = 40 = 4 € per piece
|
without projection
|
with projection
|
1. operation: 10 minutes, 10 pieces reported
2. operation: 10 minutes, 5 pieces reported
|
20 €
+ 20 €
= 40 € : 5 = 8 €/Piece
|
10 €
+ 10 €
= 20 € : 5 = 4 €/piece
|
1. operation: 10 minutes, 10 pieces reported
2. operation: 10 minutes, 10 pieces reported
|
20 €
+ 20 €
= 40 €
- 40 € (of first posting)
= 10 € : 5 = 2 €/pieces
|
20 €
+ 20 €
= 40 € : 10 = 4 €/piece
|
This example shows the difficulties of partial postings without projection. The first 5 pieces are valued at 6€, the next 5 pieces at 2€. In certain configurations even negative evaluations are possible.
Material evaluation example:
A BOM item has a requirement of 1 per 1 assembly and a value of 3€
Production quantity = 10
|
Without projection
|
With projection
|
Material issue total 10 pcs
|
10 * 3 = 30€
|
10 * 3 = 30€
|
first partial posting 1 pc
|
Posting 30€
|
Conversion to planned quantity, in this case 1/10 = Factor 0,1
30€ * 0,1 = 3€
|
second partial posting 1 pc
|
Posting 30€ - already posted = 30€ = 0€ !!
|
Conversion to planned quantity, in this case 1/10 = Factor 0,1
30€ * 0,1 = 3€
|
last posting and order completion
|
Posting 30€ - already posted= 30€ = 0€ !!
|
Not the projection but the accrued costs are used.
30 € - already posted = (3€ + 3€ = 6€) 24 €
|
Webinar Product Cost determination from 2017/06, Part "Quantity Projection"
Post-calculation – Concepts
Example: Projection of actual costs
Help URL: https://help.beascloud.com/beas202103/index.html?hochrechnung.htm
|